Final day today of 2 day irrigation blowout using air compressor hooked into pipes |
The rain continued on Monday which added to the accumulated rain to over 3.25" in the last week. Yesterday despite the rainy forecast we missed any rainfall which was a nice break to help the course catch up with draining the property and get some work done.
The fairway solid tyne aeration was completed yesterday with a total of roughly 40 man hours to complete the process.
 |
Solid tine aeration completed Tuesday |
Course hardware is currently being brought in off the property for winter maintenance and storage. All wood products are washed down, lightly sanded and re-treated with Cetol before the end of the year on poor weather days when we can't be out on the course.
 |
Course hardware brought in for refinishing/storage |
The irrigation system is being blown out the last couple of days and should be completed by the end of the day.
 |
Air being blown through irrigation lines to remove water |
Gypsum is being applied onto the fairways and green surrounds.
The comm wire installation has made it's way down the hill to the clubhouse and we should be into the buildings in a few more days once the installation starts back up next week.
 |
Comm wire install down near clubhouse |